Feeds:
Posts
Comments

Archive for September, 2007

 

PUBLIC FORUM
on the future of the
PROVIDENCE PUBLIC SCHOOLS
from the
CITY AND STATE PERSPECTIVES

Martin Luther King, Jr. Elementary School
35 Camp Street
Wednesday, Oct 17th
7:00-8:30 p.m.

SPEAKERS:
State Representative Edith Ajello
R.I. House Majority Leader Gordon Fox
State Senator Rhoda Perry
Representative David Segal
City Councilman Clifford Wood
City Councilman Seth Yurdin

Co-sponsored by
The East Side Public Education Coalition &
The Martin Luther King P.T.O.

Read Full Post »

Nathan Bishop Timetable and Milestones

 

We are grateful to Councilman Cliff Wood for providing the timetable for progress on Nathan Bishop, below. Cliff has done a great job of facilitating communication among the City, School Department and the community. We’re encouraged about the likelihood of being able to keep to the timetable by the hard work and openness we’ve seen on the part of City and PPSD officials who have been involved.  It’s fair to say, though, that this schedule is very tight- much tighter than the schedule we were looking at last spring. Therefore, it will be necessary to do everything possible to make sure that the milestones are met according to schedule.

Nathan Bishop Middle School
Project Schedule Milestones

DESIGN

Hazmat Survey Complete—September 14, 2007

Schematic Design Complete—August 31, 2007

Design Development Complete—October 31, 2007

Construction Documents Complete—January 30, 2008

FUNDING

RIDE Stage 1 Submission—August 31, 2007

RIDE Stage 1 Approval—September 17, 2007

RIDE Stage 2 Submission—October 17, 2007

RIDE Stage 2 Approval—November 21, 2007

Bond Issuance—January 31, 2008

BID / AWARD

Advertise / Issue Bid Documents—February 4-11, 2008

Bids Received—March 11, 2008

Public Opening (Board of Contracts and Supply)—March 17, 2008

Award Contract (Board of Contracts and Supply)—March 31, 2008

Contract Executed (PBA)—April 14, 2008

CONSTRUCTION

Start—April 15, 2008

Complete—July 25, 2009